  • Project Daedalus

    • Reference: 2012/0070-2
    • Question by: Caroline Pidgeon
    • Meeting date: 20 December 2012
    I wanted to pick up first on Project Daedalus and then moving forward on that. Obviously in the detailed evaluation report that we have had it showed the reoffending rate for those leaving the Heron Unit was 53%, whereas the national reoffending rate was 70%, but that was only for the first cohort. I am wondering, are you going to be looking at the later cohorts to assess what their reoffending rate was - which would mean we probably would not get the final details until the end of next year?
  • MOPAC consultations

    • Reference: 2012/0061-2
    • Question by: Caroline Pidgeon
    • Meeting date: 29 November 2012
    I want to ask about, and we have touched on it a little bit, the consultation that is going to be taking place and is taking place on the Local Policing Model, the Estate Strategy and the Police and Crime Plan. We have heard so many different things about this, perhaps, Stephen, if we could just start off with you, if you could just clarify to us exactly what will be consulted on in January. I think you said 7 January. What is going to be in it in terms of will there be options around the estate, will there...
  • Peel Centre

    • Reference: 2012/0047-2
    • Question by: Caroline Pidgeon
    • Meeting date: 27 September 2012
    I just want to pick up that with the big redevelopment of your training facilities up at Hendon, I was just wondering, there are huge challenges there I think over the next three years. You are going to have to take staff and trainees off that site while it is rebuilt. A very brief update - you might want to send more details in writing - on progress so far. For the Deputy Mayor, do you think you have the relevant staff within your Mayor's Office for Policing and Crime to manage a project on this scale? I am wondering...
  • Police Stations

    • Reference: 2012/0026-2
    • Question by: Caroline Pidgeon
    • Meeting date: 21 June 2012
    I had wanted to ask the Commissioner about police stations following what Stephen had said about how he was going to look at reviewing potential closure of police stations and the Mayor confirmed a change to his front counters policy, to find out what work is going on. But, Stephen, in your three weeks you have been there, what work have you discovered that has been going on in terms of selling the police estate across London?
  • Diamond Jubilee

    • Reference: 2012/0029-2
    • Question by: Caroline Pidgeon
    • Meeting date: 21 June 2012
    I would like to ask about the Diamond Jubilee and what lessons were learnt in terms of policing and policing tactics for the Jubilee and how those are going to help inform the plans for the Olympics.
  • Taser

    • Reference: 2012/0034-2
    • Question by: Caroline Pidgeon
    • Meeting date: 21 June 2012
    I want to move on and pick up the issue of Taser. I presume you have a briefing sheet there on Taser.
  • Legacy Master plan for the Olympic Park (Supplementary) [1]

    • Question by: Dee Doocey
    • Meeting date: 10 November 2007
    And what is the answer to my question? Why did nobody provide coaches, buses or train tickets and depend on the parents driving 300-mile round trips every weekend?
  • Legacy Master plan for the Olympic Park (Supplementary) [3]

    • Question by: Dee Doocey
    • Meeting date: 10 November 2007
    My final question is to Seb. Seb, does it worry you, as I am sure it should, that we keep reading things in the press about divers having to go to Sheffield and cyclists having to drive round the M25 in rush hour during the week in order to be able to train? Nobody could have foreseen that there were going to be problems with Crystal Palace? Surely these are the people that you are trying to inspire; these are the people that you are reaching out to so successfully. Once you realised that these people had to go to...
  • Mitigating the Games-time Environmental Impact (Supplementary) [2]

    • Question by: Mike Tuffrey
    • Meeting date: 10 November 2007
    Can I go back to the sustainability announcement that was alluded to earlier and is presumably what you were just referring to, Seb. What is that? Is that further commitments or is that the reality behind the commitments that have already been given? That is the first question. Then in terms of the scope of it, you have said it was kind of biodiversity and so forth, but is it sustainability in an economic, social and environmental sense or is it essentially still environmental-related commitments?