Meeting: | Plenary on 06 September 2018 |
Session name: | Plenary on 06/09/2018 between 10:00 and 13:00 |
Question by: | Caroline Pidgeon |
Organisation: | Liberal Democrats |
Asked of: | Mike Brown (Commissioner, Transport for London) |
Question
Lead off question - Delays to Crossrail (Supplementary) [4]
Caroline Pidgeon MBE AM: Finally, time is money in the construction sector. There will inevitably be an additional cost with this delay. Who is going to be picking up that bill, is it TfL and Londoners or is it going to be the DfT?
Answer
Mike Brown MVO (Commissioner, Transport for London): Obviously, it is early days in terms of the assessment of any additional cost over and above the £300 million that was agreed in the written Ministerial Statement from the Transport Minister that the Mayor, as Chair of the TfL Board, had authorised the sign‑off for, and which we had made provision for within our budget in year to ensure we could deliver that. However, I will tell you and the rest of your Assembly Member colleagues that I have a meeting this afternoon with the DfT and Her Majesty’s Treasury to, of course, explore potential further challenges and how we work together collectively to ensure we can address those.
On this page
Related questions
Question | Reference | Date |
---|---|---|
Lead off question - Delays to Crossrail (Supplementary) [1] | 6 September 2018 | |
Lead off question - Delays to Crossrail (Supplementary) [2] | 6 September 2018 | |
Lead off question - Delays to Crossrail (Supplementary) [3] | 6 September 2018 | |
Lead off question - Delays to Crossrail | 2018/2507 | 6 September 2018 |
Lead off question - Delays to Crossrail (Supplementary) [5] | 6 September 2018 | |
Lead off question - Delays to Crossrail (Supplementary) [6] | 6 September 2018 | |
Lead off question - Delays to Crossrail (Supplementary) [7] | 6 September 2018 | |
Lead off question - Delays to Crossrail (Supplementary) [8] | 6 September 2018 | |
Lead off question - Delays to Crossrail (Supplementary) [9] | 6 September 2018 | |
Lead off question - Delays to Crossrail (Supplementary) [10] | 6 September 2018 |