Executive summary

In June 2019 the Mayor agreed a standing delegation to the Assistant Director Planning to enter into bespoke Planning Performance Agreements (PPAs) for complex planning schemes up to a cap of £250,000 on a cost recovery basis from the developer to cover GLA officer, and if required consultant, costs. The delegation was to be exercised through an ADD decision form for each PPA.

A PPA for £30,000 has been agreed with the developer of the Knolly’s Yard scheme.

Decision

That the Assistant Director, Planning approves:

1. The Planning Performance Agreement in respect of the Knolly’s Yard scheme; and

2. The receipt of £30,000 on a cost recovery basis from the developer Prime Place Tulse Hill LLP.

Part 1: Non-confidential facts and advice

1.1 Planning Performance Agreements were formally introduced into the planning system on 6 April 2008 and are principally aimed at major planning applications that need substantial amounts of officer time and negotiation throughout the life of the scheme and allow officers to improve the quality of schemes that are eventually submitted as planning applications and determined. They also allow the GLA to charge for officer time taken up by the larger scale strategic schemes.

1.2 A Mayoral decision (MD2475) on 11 June 2019 gave delegated authority to the Assistant Director to enter into Planning Performance Agreements (PPAS) up to a cap of £250,000.

2.1 The principal objective is to maintain an effective high-quality strategic planning service at a time of pressure on resources and growing external and corporate demands by ensuring there are sufficient resources to deal with pre-application advice and applications including call ins by the Mayor. The expected outcomes are:

• a continuation of the ability to deal with increasing workloads particularly the pre-application service by having sufficient resources in place; and

• allowing the GLA planning function to keep up with high and rising levels of demand for advice whilst delivering an efficient fit for purpose strategic planning function for the Mayor.

3.1 Under section 149 of the Equality Act 2010, in making these decisions “due regard” must be had to the need to eliminate unlawful discrimination, harassment and victimisation as well as to advance equality of opportunity and foster good relations between people who have a protected characteristic and those who do not. Protected characteristics include age, disability, gender reassignment, pregnancy and maternity, race, religion or belief, gender, sexual orientation (and marriage or civil partnership status for the duty to eliminate unlawful discrimination only). In this instance the proposals have been considered and are not expected to have any impacts on those with protected characteristics as distinct from anyone else.

Mayoral strategies and priorities:

4.1 Pre-application advice is fundamental to the implementation of the Mayor’s London Plan which seeks to ensure that the city meets the challenges of economic and population growth with much needed housing and commercial floorspace along with other associating social infrastructure and transport infrastructure to enable the development. The Mayor’s comments and decisions on referable planning applications is a key implementation tool of the London Plan. The pre-application service helps to ensure subsequent applications deliver London Plan objectives.

Risk management issues:

4.2 Regular monitoring of income will be necessary to ensure the costs of providing the service are covered and the income is spent within the Regulations associated with the Local Government Act.

Conflicts of interest

4.3 There are no conflicts of interest to note for any of those involved in the drafting or clearance of the decision.

5.1 Approval is being sought for expenditure of up to £30,000 for a Planning Performance Agreement (PPA) in respect of the Knolly’s Yard scheme, and the receipt of £30,000 on a cost recovery basis from the developer, Prime Place Tulse Hill LLP.

5.2 The PPA income and associated expenditure is budgeted for in 2021-22 within Planning Unit budgets.

5.3 The costs on this agreement will be capped and any additional work required on the scheme over the approved amount will be subject to further approval via the Authority’s decision-making process.

Activity

Timeline

Completion of Planning Performance Agreement

End July 2021

From early May and through June and July meetings to discuss development of a viable redevelopment scheme.

Early May-end July 2021

Signed decision document

ADD2516 Knollys Yard Planning Performance Agreement - SIGNED

Need a document on this page in an accessible format?

If you use assistive technology (such as a screen reader) and need a version of a PDF or other document on this page in a more accessible format, please get in touch via our online form and tell us which format you need.

It will also help us if you tell us which assistive technology you use. We’ll consider your request and get back to you in 5 working days.