Skip to main content
Mayor of London logo London Assembly logo
Home

FOI - Construction and building maintenance contracts

Key information

Request reference number: 2273

Date of response:

Summary of request

Please find attached and below our FOI request

For any questions regarding this FOI, please do not hesitate to get in touch.

Starts

1.    For construction and building maintenance contracts established since 1 January 2017, have you, or will you be putting in place monitoring and reporting whether your main contractors/suppliers are paying their sub-contractors/suppliers within 30 days? [Please choose]

A)   We are already monitoring and reporting that payment takes place within 30 days routinely

B)   We will be monitoring and reporting that payment takes place within 30 days routinely

C)   We don’t and will not be monitoring and reporting that payment takes place within 30 days

D)   If you don’t know, please provide information on what policy you do pursue

2.    For construction and building maintenance contracts established since 1 January 2017, have you built in a contractual requirement for your suppliers to pay the suppliers directly below them in the supply chain within 30 days (or are you taking steps to apply this)? [Please choose]

A)   We have built in a contractual requirement for payment to flow through the supply chain within 30 days routinely

B)   We are taking steps to apply a contractual requirement for payment to flow through the supply chain within 30 days routinely

C)   We have not and will not be building in a contractual requirement for payment to flow through the supply chain within 30 days

D)   If you don’t know, please provide information on what policy you do pursue

3.    For construction and building maintenance contracts established since 1 January 2017, do you deduct cash retentions from your main contractors/suppliers? [Please indicate any answers that describe your current position – it could be more than one]

A). We do not deduct cash retentions

B). We deduct cash retentions up to 5%

C). We deduct retention above 5%

4. When you regularly deduct cash retentions, do you use the cash:

[Please indicate any answers that describe your current position – it could be more than one]

A). To bolster your working capital

B). To fund other construction-related activities

C). To fund other activities (not related to construction)

D). To invest in overnight money markets

E) OTHER: Please specify

5. For construction and maintenance contracts established since January 2017:

[Please choose]

A). If you do not deduct cash retentions, do you insist that your main supplier/contractor does not deduct cash retentions from their sub-contractors/suppliers too.

B). You do not impose any contractual requirements on your main suppliers about cash retentions from their sub-contractors/suppliers

C). OTHER: Please specify​

Related documents

Need a document on this page in an accessible format?

If you use assistive technology (such as a screen reader) and need a version of a PDF or other document on this page in a more accessible format, please get in touch via our online form and tell us which format you need.

It will also help us if you tell us which assistive technology you use. We’ll consider your request and get back to you in 5 working days.