Skip to main content
Mayor of London logo London Assembly logo
Home
London Assembly

Old Street Roundabout Project

Label Content
Meeting: MQT on 15 December 2022
Session name: MQT on 15/12/2022 between 10:00 and 13:00
Reference: 2022/5350
Question by: Keith Prince
Organisation: City Hall Conservatives
Asked of: The Mayor
Category: Transport

Question

Old Street Roundabout Project

What is the current estimated cost to TfL of the Old Street Roundabout Project, what are the causes of the delay, and what is TfL's precise role in the scheme?

Answer

Date: Tuesday 20 December 2022

TfL is accountable for the delivery of the project. The current Programme and Project Authority is £112 million, with roughly 1/3 of the cost for the highway works and 2/3 for the underground works connected to the station entrance and retail concourse.

This is an extremely complex project in a busy location on the Inner Ring Road above an Underground and Network Rail station. A key requirement of the project has been for the road and station to remain open and accessible throughout the works, which has further complicated delivery. 

While good progress has been made, there remain cost and programme pressures that TfL is currently working hard to address with its principal contractor.

The project has experienced several delays for multiple reasons, including the impact of the coronavirus pandemic, which shut the site for three months, followed by months of social distancing measures, which, in such a confined work site, significantly added to delays. 

The condition of the underground assets was found to be poor, resulting in significant additional work to ensure compliance with fire and electrical safety standards, and to provide an essential upgraded power supply. The contractor uncovered a range of previously uncharted utilities, which required safe and controlled removal before further work could continue.

Related questions

Question Reference Date
Old Street Roundabout 2013/2348 17 July 2013
The Old Street Project 2014/1931 11 June 2014
Old Street Roundabout (1) 2013/3599 23 October 2013
Old Street Roundabout (2) 2013/3600 23 October 2013
Old Street Roundabout (3) 2013/3601 23 October 2013
Old Street Roundabout (4) 2013/3602 23 October 2013
Air Quality at Old Street Roundabout 2009/1178 21 May 2009
Plans for Old Street roundabout (1) 2013/0112 30 January 2013
Plans for Old Street roundabout (2) 2013/0113 30 January 2013
Old Street roundabout – rejection of crossroads option 2014/3006 10 September 2014