Hammersmith Bridge

Meeting: 
Plenary on 2019-02-07
Session date: 
February 7, 2019
Reference: 
2019/2086
Question By: 
Caroline Pidgeon
Organisation: 
Liberal Democrats
Asked Of: 
Sadiq Khan (Mayor of London) & Mike Brown MVO (Commissioner, Transport for London)

Question

Your reply to MQ 2018/2997 in November of last year stated that 'more clarity will be available at the end of the year’ as to when repair and strengthening work of the bridge will finally commence. Following no information being provided by the end of 2018 please provide an update.

 

Answers

Answer for Hammersmith Bridge
Hammersmith Bridge

Hammersmith Bridge

Answered By: 
The Mayor

The London Borough of Hammersmith and Fulham received a report from the appointed consultants in December, and the borough made the report available to Transport for London for review. A number of clarification points have been raised and these need to be satisfactorily resolved before a preferred option can be selected and a programme developed.

One of the points relates to the detailed engineering assessment of the bridge cables and pins – it has been agreed that further assessment is required to robustly conclude the options analysis and cost assessment.

It is estimated that this further investigation work will be completed in Spring 2019.