Transport Strategy – Step-free access (2)

Meeting: 
MQT on 2019-06-20
Session date: 
June 20, 2019
Reference: 
2019/12248
Question By: 
Navin Shah
Organisation: 
Labour Group
Asked Of: 
The Mayor

Question

As part of the Accessibility Implementation Plan, a target for delivery of 25 step-free tube stations was set from 2020-2025 and a further 15 from 2025-2030, have these tube stations been identified? Please give us a list.

Answer

Transport Strategy – Step-free access (2)

Transport Strategy – Step-free access (2)

Answered By: 
The Mayor

Transport for London (TfL) continues to deliver the step-free access programme, which runs until 2024. Stations to be made step-free by 2020 are Amersham, Harrow-on-the-Hill, Cockfosters, Mill Hill East, Osterley, Burnt Oak, Debden, Northolt, Sudbury Hill, Wimbledon Park, Hanger Lane and Ickenham. Their completion by 2020 will mean that more than a third of the Tube network will be step-free.

A second tranche of six stations that are part of my accessibility programme will be made step-free by Spring 2024. They are Boston Manor, Ruislip, North Ealing, Snaresbrook, Park Royal and Rickmansworth.

Step-free access work is progressing at vital interchanges like Bank. The Northern line extension will provide another two new step-free stations at Nine Elms and Battersea Power Station. All 41 Elizabeth line stations will be step-free.

TfL will confirm any further rollout of step-free upgrades when the level of capital investment funding from Government is more certain.