100 Avenue Road (2)

Meeting: 
MQT on 2018-11-22
Session date: 
November 22, 2018
Reference: 
2018/3379
Question By: 
Andrew Boff
Organisation: 
GLA Conservatives
Asked Of: 
The Mayor

Question

Further to question 2018/2627, please provide justification that the plan to simultaneously construct CS11 and 100 Avenue Road will reduce the overall impact on the transport network when specifically considering the negative impacts on the Swiss Cottage Open Space and Swiss Cottage residents.

Answer

100 Avenue Road (2)

100 Avenue Road (2)

Answered By: 
The Mayor

Constructing 100 Avenue Road and CS11 simultaneously would shorten the overall works duration by 18 months, reducing overall disruption to Swiss Cottage residents and maintaining provision of bus stops outside Swiss Cottage Underground Station.