Following on from Question No: 2018/2805, what assessment has been made of the resilient track fixing in Mornington Crescent, where repeat complaints on the Bank Branch between Euston and Camden Town have been logged, owing to an increase in noise again after the resilient fixings were installed?

Answer

Tube noise [4]

Tube noise [4]

Answered By: 
The Mayor

At Mornington Crescent, Transport for London (TfL) completed the installation of further resilient track fastenings – and rail joint removal - in October 2018. The resilient track fastenings have significantly reduced noise levels, and the majority of noise complaints have now been closed.

TfL is currently assessing what further options to reduce noise levels are available at this location.