Homes on TfL Land (10)

Meeting: 
MQT on 2018-02-22
Session date: 
February 22, 2018
Reference: 
2018/0476
Question By: 
Tom Copley
Organisation: 
Labour Group
Asked Of: 
The Mayor

Question

In March 2014, Capco and TfL established Joint Venture to develop Earls Court 1 & 2 and provide 7,500 homes. 1,800 of those homes feature in the 10,000 homes target announced in March 2016. What is the timescales for delivery of these homes and how many of the 1,800 homes will be affordable?

Answer

Answer for Homes on TfL Land (10)

Answer for Homes on TfL Land (10)

Answered By: 
The Mayor

Demolition of the former Earls Court exhibition centres and removal of the portal beams has just been completed and the joint venture is considering the first phase of development to be brought forward.

The existing consent was granted under my predecessor's administration and includes around 165 affordable homes. I would expect any revised masterplan coming forward to have substantially more affordable housing.