Better junctions review programme (5)

Meeting: 
MQT on 2015-11-18
Session date: 
November 18, 2015
Reference: 
2015/3700
Question By: 
Darren Johnson
Organisation: 
City Hall Greens
Asked Of: 
The Mayor
Category: 

Question

In the response to 2015/0737 that you provided in March 2015 you stated that 86 junction reviews had been completed. The Better Junctions Summary dated 23rd September states that 86 reviews have now been completed. Why did TfL make no progress in completing reviews of junctions on its top 100 list over these six months?

Answer

Answer for Better junctions review programme (5)

Answer for Better junctions review programme (5)

Answered By: 
The Mayor

The junction reviews are part of an extensive programme of work being designed and delivered by TfL which includes the Cycle Superhighways and major schemes at Elephant & Castle, Oval, Stockwell and Vauxhall Cross to name but a few. As a result of this work we are now transforming London's roads to be fit for a 21st Century city.

All remaining locations on the original list of better junctions will be reviewed by the end of 2015.