What is the cost contingency of the proposed two-way scheme at Baker Street?

Answer

Answer for Baker Street two-way proposal (4)

Answer for Baker Street two-way proposal (4)

Answered By: 
The Mayor

The proposed two-way scheme at Baker Street has a budgeted cost contingency of 15 per cent of the expected total cost of the scheme. This is encompassed in the total budget for £15m for the Baker Street scheme.