Can you provide me with an update on the Access for All works at South Tottenham station?

Answer

Answer for South Tottenham

Answer for South Tottenham

Answered By: 
The Mayor

Work is now progressing well to provide step-free access at South Tottenham station. The lift shafts have been completed and the installation of the lifts is well underway. Work has commenced on improving the station entrance and staff accommodation. TfL expects the work to be completed, with the lifts and new station entrance fully open to passengers, by the end of the year.