How much new decentralised energy generation is predicted to come forward in London as result of your new Licence Lite status?

Answer

Answer for Licence Lite (2)

Answer for Licence Lite (2)

Answered By: 
The Mayor

The level of response to the GLA's prequalification questionnaire to decentralised energy generators received in June 2015 is encouraging and indicates that the prospects of licence lite helping to bring forward substantial amounts of new decentralised energy are promising.

A target building up to 100 MW of new decentralised energy capacity by the end of the first three years of licence lite operation would not be unreasonable, but that would not limit future expansion when feasible.