When will the first power be supplied to Transport for London (TfL) as a result of your new Licence Lite supplier status? What proportion of TfL's total electricity demand will this equate to?

Answer

Answer for Licence Lite (1)

Answer for Licence Lite (1)

Answered By: 
The Mayor

The date when the first power can be supplied to TfL is currently being negotiated with TfL and their current electricity suppliers. Power will be supplied in stages, as TfL's current supply arrangements are released. Discussions are directed at beginning the supplies during the autumn of this year.

The objective is that supplies to TfL will build up to about 10MW during the first year of operation, amounting to approximately 23 per cent of their low voltage electricity requirements.