Garden Bridge (2)

Meeting: 
MQT on 2015-07-15
Session date: 
July 15, 2015
Reference: 
2015/2040
Question By: 
Caroline Pidgeon
Organisation: 
Liberal Democrats
Asked Of: 
The Mayor
Category: 

Question

Following the decision of Sir Peter Hendy to instruct that a review of the overall process of procurement of the Garden Bridge design contracts is undertaken, will you ensure that no construction work commences on the proposed bridge until the review is fully completed and published?

Answer

Answer for Garden Bridge (2)

Answer for Garden Bridge (2)

Answered By: 
The Mayor

Construction of the Garden Bridge is not expected to begin until early 2016. Therefore, the findings of the review will be published prior to the commencement of construction work.