Decentralised Energy Projects

Meeting: 
MQT on 2015-03-25
Session date: 
March 25, 2015
Reference: 
2015/1016
Question By: 
Murad Qureshi
Organisation: 
Labour Group
Asked Of: 
The Mayor
Category: 

Question

Please provide an update on the current status of all decentralised energy projects referenced on pages 16/17 of your Climate Change Mitigation and Energy Annual Report of March 2014.

Answer

Answer for Decentralised Energy Projects

Answer for Decentralised Energy Projects

Answered By: 
The Mayor

The current status of the projects you refer to is as follows:

•       Camden's Gospel Oak CHP Network: this scheme is operational.

•       Brent's South Kilburn Combined Heat and Power District Heating (CHPDH) scheme: this project has re-advertised the opportunity.

•       Goldsmith's College CHPDH Scheme - the decision to proceed with CHP heat network procurement is awaiting the outcome of the feasibility study for a new building.

•       Camden's Euston Road CHPDH Scheme: this project has appointed a contractor for its design, build and operation.

•       Crystal Palace CHP: this project is operational.

•       Bunhill CHP: this project is operational and is now planning it's expansion.

•       Queen Elizabeth Olympic Park District Energy Network: this scheme is operational.

•       South East London Combined Heat and Power (SECHP) : this district heating scheme is operational.