Pelican crossing, Colindeep Lane

Meeting: 
Plenary on 2014-09-10
Session date: 
September 10, 2014
Reference: 
2014/3041
Question By: 
Andrew Dismore
Organisation: 
Labour Group
Asked Of: 
Boris Johnson (Chair, TfL) and Sir Peter Hendy (Commissioner, TfL)

Question

Despite repeated assurances, this crossing has still not been installed. What is the hold up now, and when will it be built?

Answer

Answer for Pelican crossing, Colindeep Lane

Answer for Pelican crossing, Colindeep Lane

Answered By: 
Boris Johnson (Chair, TfL) and Sir Peter Hendy (Commissioner, TfL)

TfL has completed the design of the crossing at Colindeep Lane adjacent to Clovelly Avenue and has shared this with the London Borough of Barnet.

Barnet is carrying out the civil engineering works, including installation of dropped kerbs, sub-surface cable ducting, tactile paving and carriageway markings, and then TfL will install the signals infrastructure.