Did the Mayor place the contract for the management of the next phase of the RE:NEW programme to competitive tender? Has the contract been awarded?

Answer

Answer for RE:NEW (2)

Answer for RE:NEW (2)

Answered By: 
The Mayor

Yes. An OJEU compliant competitive procurement exercise for a service provider to deliver the RE:NEW Support Team was conducted using TfL's Engineering and Project Management Framework (EPMF) TfL 90001.  Capita Symonds has been selected, subject to contract.