Will the Mayor update the Assembly on the timetable for all Tube upgrades?

Answer

Answer for Tube Upgrades

Answer for Tube Upgrades

Answered By: 
The Mayor

Waterloo & City line - upgrade completed in 2006, as planned.

Jubilee line - Tube Lines' contractual completion date is 2009, however it has become clear that the programme has slipped and completion is not now expected until well into 2010.

Northern line - Tube Lines' contractual completion date is the beginning of 2012.

Victoria line - contractual complete date is 2013; due for completion in 2012.

Piccadilly line - contractual completion date is 2014.

Sub-Surface lines (Circle, District, Hammersmith & City, Metropolitan) - due for completion in 2018.

Bakerloo line - due for completion in 2020.