Bus Route Performances 3

Meeting: 
MQT on 2009-11-18
Session date: 
November 18, 2009
Reference: 
2009/3377
Question By: 
Valerie Shawcross
Organisation: 
Labour Group
Asked Of: 
The Mayor

Question

Please list in order the 10 worst routes for reliability performance against scheduled timetable, according to the most recent data.

Answer

Answer for Bus Route Performances 3

Answer for Bus Route Performances 3

Answered By: 
The Mayor

This is set out below. In each case TfL is working with the relevant operator to identify solutions to the performance difficulties which exist. A number of routes have been affected by road works which are due to finish soon, particularly so in the case of route R70.

Route Minimum Standard* Current Performance* 228 1.10 2.55 150 1.30 2.43 30 1.70 2.30 65 1.50 2.03 R70 1.30 1.94 381 1.50 1.84 158 1.30 1.82 145 1.10 1.81 366 1.30 1.81 C10 1.10 1.80

*Note: this represents Excess Waiting Time, which is calculated by subtracting actual waiting time from scheduled waiting time.