Cycle superhighways (2)

Meeting: 
MQT on 2009-11-18
Session date: 
November 18, 2009
Reference: 
2009/3152
Question By: 
Jenny Jones
Organisation: 
City Hall Greens
Asked Of: 
The Mayor

Question

What is the cost breakdown on the £22m for the two pilot Cycle Superhighways?

Answer

Answer for Cycle superhighways (2)

Answer for Cycle superhighways (2)

Answered By: 
The Mayor

Answer from the Mayor: This is set out in the table below.

£ million Route 3 Route 7 Total Infrastructure costs 3.27 5.53 8.80 Design, legal, property, management and monitoring costs 1.30 1.75 3.05 'Smarter travel' costs ('home' and 'work' end measures including cycle parking, work facilities, training, information and communication) 2.90 2.91 5.81 Risk and contingency 2.05 3.28 5.33 Total 9.52 13.47 22.99