Do you think that there were any options for dealing with the overspend on Olympic land acquisition? Were you consulted on what the options were and, if so, what was your position?

Answer

Answer for Olympic land acquisition

Answer for Olympic land acquisition

Answered By: 
The Mayor

I was fully consulted on all options available to deal with the forecast overspend - these include reductions to programmes, increases in capital receipts & deferral of ODA expenditure.