Green Homes Programme

Meeting: 
MQT on 2009-02-25
Session date: 
February 25, 2009
Reference: 
2009/0221
Question By: 
Darren Johnson
Organisation: 
City Hall Greens
Asked Of: 
The Mayor

Question

How long would an innovative project such as the Green Homes Programme normally have to run before a full evaluation could be made of its success and future potential?

Answer

Answer for Green Homes Programme

Answer for Green Homes Programme

Answered By: 
The Mayor

All LDA projects are subject to evaluation on completion and many projects also undergo a mid-term evaluation. If a project is underperforming and/or is not meeting contractual targets, the project will be evaluated no matter what stage it has reached.

The LDA undertook an evaluation of the Green Homes Concierge Service in September 2008 due the project not meeting contractual targets. The results of the evaluation are being used by the GLA and LDA to inform the development of a pan London home energy efficiency scheme that will reach far more households, and build on the lessons of the existing concierge service.