Can you detail at what negotiating stage London Underground are at with Network Rail over the parts of the network that are shared, in relation to the extended opening hours? Is there any substance to the allegations that the lack of agreement could push the extended opening to 2008?

Answer

Answer for Tube Late Night Opening

Answer for Tube Late Night Opening

Answered By: 
The Mayor

Network Rail supports the later running of the Tube and arrangements for the north-end of the Bakerloo have already been finalised. Detailed arrangements for access to the Richmond branch are in progress and expected to be resolved very shortly.