Rail and Tube Maintenance

Meeting: 
MQT on 2006-11-18
Session date: 
November 18, 2006
Reference: 
2006/2158
Question By: 
Geoff Pope
Organisation: 
Liberal Democrats
Asked Of: 
The Mayor

Question

How often do TfL meet with Network Rail to coordinate rail and tube maintenance closures in order to minimise disruption?

Answer

Answer for Rail and Tube Maintenance

Answer for Rail and Tube Maintenance

Answered By: 
The Mayor

Every 3 months, LU and NR meet to coordinate planned closures and a joint programme is in place ' which currently looks ahead to 2008. Of course, where a substantial programme of closures is needed for specific events, LU and NR meet on a more frequent basis. In addition, LU and NR meet jointly with stakeholders such as Wembley Stadium and Twickenham Stadium, to coordinate closures around major events at these venues.