Twickenham Bridge A316

Meeting: 
Plenary on 2006-12-06
Session date: 
December 6, 2006
Reference: 
2006/0460
Question By: 
Tony Arbour
Organisation: 
GLA Conservatives
Asked Of: 
Peter Hendy (Commissioner, Transport for London)

Question

What is TfL's timetable for re-arranging the meeting with English Heritage, scheduled to have taken place in February of this year, to discuss the repair work that needs to be carried out to the Twickenham Bridge (A316)?

Answer

Answer for Twickenham Bridge A316

Answer for Twickenham Bridge A316

Answered By: 
Peter Hendy (Commissioner, Transport for London)

Refurbishment of Twickenham Bridge is programmed to take place in 2007/8. Consultation with all stakeholders, including English Heritage, is planned to commence early in 2007 before design work starts in April 2007. We plan to meet English Heritage early in the New Year, and there was no meeting scheduled to take place with them in February.