How are matters progressing with the Coulsdon Inner Relief Road/Coulsdon Town Centre Improvement scheme? .

Answer

Answer for Coulsdon Inner Relief Road

Answer for Coulsdon Inner Relief Road

Answered By: 
Ken Livingstone

The contract for construction of the new road around Coulsdon town centre was awarded to the developer on 23 December last year. Work is programmed to start on the site at the end of this month or early in February. On phase two of the scheme, improvements to Brighton Road are planned to commence after the opening of the new road and traffic has been diverted. Croydon Council is currently being consulted on the design brief for these later works. .