Cross River Tram Project

Meeting: 
MQT on 2003-12-17
Session date: 
December 17, 2003
Reference: 
2003/2367
Question By: 
Lynne Featherstone
Organisation: 
Liberal Democrats
Asked Of: 
The Mayor

Question

What progress has Transport for London made in developing the Cross River Tram Project (Camden to Peckham) and what is your current projection of the date by which it can begin operating?

.

Answer

Answer for Cross River Tram Project

Answer for Cross River Tram Project

Answered By: 
The Mayor

TfL is currently assessing all of the technical, traffic, economic, social and environmental aspects of Cross River Transit, and is fully engaged with the Boroughs, the Cross River Partnership, and with their own internal stakeholder groups in taking this project forward.Subject to the appraisal proving sufficiently positive, and a commitment to the expenditure from Government, the project could be delivered by 2011at the earliest. .