Mayoral decisions

9 August 2013

The Centre for Engineering and manufacturing Excellence (CEME) is a not-for-profit education and skills centre at Rainham, in the London Borough of Havering, which provides a focus on supporting the engineering, manufacturing and technology sectors. CEME brings together a range of organisations...

9 August 2013

The London Assembly’s Audit Panel meets four times a year and considers reports from the Greater London Authority’s (GLA) internal and external auditors. After each meeting, those audit reports are noted by the Mayor in his executive oversight role at the GLA. The 16 July 2013 meetin...

9 August 2013

GLA Land & Property Ltd (GLAP) inherited a number of significant Compulsory Purchase Order (CPO) programmes in April 2012 including those associated with the Olympic Park, Wembley Stadium, Silvertown Way and a range of smaller projects. The GLA has entered into a shared service arrangement w...

9 August 2013

Approval is sought to deliver three projects that demonstrate the value of digital solutions, systems integration and collaborative business models in the evolution of London as a leading Smart City. The projects will use GLA funding released following a grant award of £3m from the Tech...

7 August 2013

The profile of the London Food Board and the workload of the Food Programme have continued to evolve requiring a considerable increase in the amount of time and accountability expected from the Chair of the Board. This request for approval revises the existing terms of appointment for the Chair...

5 August 2013

The London Fire Commissioner presented his proposals for the final Fifth London Safety Plan 2013-2016 to the 18 July 2013 meeting of the London Fire & Emergency Planning Authority (“LFEPA”). LFEPA resolved to remove all references to reductions in the numbers of firefighters, fire stations a...

31 July 2013

The GLA is in litigation with ‘The Claimants’ who had their land acquired under compulsory purchase powers.

This report sets out the terms for a letter to settle with the Claimant and protect the GLA from costs.

Following negotiation with a CPO claimant the GLA has reac...

31 July 2013

Following negotiations with a CPO claimant the GLA has reached a provisional settlement of terms for compensation with ‘the Claimant’. This report sets out the terms for the agreement and seeks authority to formally agree those terms and settle the claim.

30 July 2013

This MD should be read in conjunction with MD1073  and further to that, this Mayoral Decision agrees that the GLA enter into contracts with the successful bidders of the £30m phase one of the Mayor’s Care and Support Specialised Housing Fund  to deliver specialised supporti...

30 July 2013

Approval is sought for £136.5m of initial allocations of funding as a contribution to recipients’ costs of delivering 6,190 homes under the “Mayor’s Housing Covenant – Building the Pipeline” programme and the delegation of authority to assist in the e...