MD2062 Revolving Investment in Cities (RICE) European Project

Key information

Decision type: Mayor

Reference code: MD2062

Date signed:

Decision by: Sadiq Khan, Mayor of London

Executive summary

The GLA has been successful in its application for Revolving Investment in Cities (RICE) European funding, which is to be used to further the development of new financial instruments that can increase private sector investment in solutions and initiatives that tackle urban development issues, in particular in relation to Smart Cities, the environment and regeneration. The total award is €2.3m, the GLA’s share of which is €245k, and the project will last for 12 months. This project will be delivered in conjunction with the City of The Hague and the Department of Communities and Local Government as main partners and Manchester City Council as an affiliate partner.

Decision

That the Mayor:

1. approves:

(a) the GLA’s receipt of €244,976 EU Revolving Investment in Cities (RICE) funding from the City of The Hague (acting as lead partner); and

(b) GLA expenditure on the RICE project of up to €257,870 (€244,976 - EU RICE funding and up to €12,894 - existing GLA staff budgets);

2. delegates authority to the Executive Director for Development, Enterprise and Environment to take all steps necessary for the GLA to deliver its contribution to the RICE project, including revisions to proposed budget allocations, as appropriate, within the overall amount approved.

Part 1: Non-confidential facts and advice

1.1 In July 2015, the GLA in partnership with the City of the Hague and the Department for Communities and Local Government (DCLG) submitted an application to the European Commission (EC) for funding for the Revolving Investment in Cities in Europe (RICE) project in response to a call for proposals under "Multi-region assistance for the assessment of the potential use of financial instruments supported by the ERDF, CF, ESF and EAFRD in accordance with Title IV of Regulation (EU) 1303/2013".

1.2 The GLA were informed on 1 December 2016 that it had been successful in its application.

1.3 The total award is €2.3m and the project will last for 12 months. The lead partner is the City of The Hague. DCLG are the other main partner, with Manchester City Council as an affiliate partner. The GLA’s share of the award is €244,976. The GLA is required to provide €12,894 match funding which will be met from existing staff budgets.

1.4 The project will explore how to increase the use of Financial Instruments (FIs) and the levels of investment (both public and private) secured and deployed through them in order to tackle urban development issues, in particular in relation to Smart Cities, the environment and regeneration. The project will build upon the work undertaken by the URBACT funded CSI Thematic Network in 2015. CSI was a network of ten European cities engaged in different capacities in the development and implementation of urban-based financial instruments. The network identified a number of themes and developed tools and guidance to facilitate the more efficient delivery of financial instruments to support urban development.

1.5 The European Investment Bank (EIB) will be commissioned by the City of The Hague to conduct analysis that will assess the market need for urban FIs, the barriers to implementation, as well as development needs and potential solutions. Following this, the feasibility of multi-regional urban FIs will be explored and initial pipeline development on one or more FIs will be undertaken. Findings will be shared with other EU regions, published and disseminated via two transnational events.

1.6 The project will help put London at the centre of commercialising innovation and prototyping technology-based solutions to urban challenges (specifically regeneration, environment and Smart City initiatives) and inform a London wide strategy on unlocking investment and leveraging private sector funding in these areas. It will help to explore and define possible roles for the GLA in new financial models of delivery and methods of harnessing the creative and innovative potential of London’s SMEs and entrepreneurs to tackle some of our most entrenched urban challenges.

1.7 The advantage of using FIs over providing grants to distribute public funding for urban initiatives is that provision is made for a proportion of the investment to be repaid, releasing funds for reinvestment in further projects in the future. Under an FI, public funding is normally managed by a private sector fund manager who is responsible for the appraisal of investments, pricing of the financial products and monitoring of the deliverables.

1.8 In addition, the advantages of FIs go beyond recycling investment funds. The requirement for professional-led investment decisions imposes a discipline that means FIs only invest in financially viable projects and increases the likelihood that FI resources are invested in deliverable schemes. It is this commercial discipline that has the potential to attract additional investment from private or public funders.

1.9 Once, additional private funding has been attracted, the risk is spread between the partners and the private sector has a vested interest in making the initiative successful. In some cases, depending on how the incentives and performance requirements are contracted, there is an appropriate risk transfer to the private sector, which can further extract long-term value-for-money for the public sector.

2.1 The RICE project is a research project which will support the development of future FIs. The specific research objectives are set out below:

Market need
• To understand the extent of shared investment priorities and financing needs in the partner geographies
• To understand what FI models have worked to date (building on evaluation work already undertaken) in the partner geographies
• To understand the extent to which these priorities and financing issues are replicable in other cities/regions elsewhere in the EU

Implementation Barriers
• To understand the complexities involved in the development and implementation of FIs – State aid framework, ability to secure private investment, balance sheet issues, pipeline development and viability, prevalence of grant, financial intermediary capacity and governance;
• This work stream will develop an understanding of the main barriers in detail in the partner geographies and will also involve scoping and consultation work to test the relevance of the issues in other regions.

2.2 Further to this analysis, the EIB will explore possible solutions to overcome the issues identified and achieve greater FI investment. It is envisaged that some of the solutions will include:

Standardised Solutions
• Development of standardised investment products;
• Development of off balance sheet financing structures;
• Development of new technical assistance products to support pipeline development work, for the partner geographies but also replicable across other regions/FIs;
• Development of state aid guidance/pre-notification, paying particular attention to addressing FI delivery in non-assisted areas.

2.3 Work will also be undertaken on initial pipeline development for a future FI and the findings will be shared with other regions with a view to exploring the potential for a multi-regional approach:

Pipeline Development
• To carry out initial pipeline development work in each of the partner geographies to develop an investment pipeline for the potential multi regional FI;
• To use the above pipeline development process to pilot the feasibility of the proposed technical assistance fund.

Transferability
• To further develop the knowledge and expertise of the partners in the set up and implementation of financial instruments;
• To develop appropriate guidance documentation to address common implementation barriers and facilitate FI implementation;
• To organise dissemination events so as to help to improve the knowledge of other managing authorities and stakeholders interested in developing FIs;
• To explore potential additional partner regions/cities for the potential multi regional FI.

2.4 The project will help inform a London wide strategy on unlocking investment and leveraging private sector funding and to put London at the centre of commercialising innovation and prototyping technology based solutions to urban challenges. This will build on the GLA’s work on Sharing Cities, which provides a testing bed for data led innovation, as well as supporting emerging strands of work such as GovTech, which would encourage entrepreneurs to build services and products aimed at the public sector in a bid to reduce costs, increase efficiency and improve service quality.

2.5 A draft budget profile, detailing the GLA expenditure, is attached in appendix 1. It is expected that €50,000 will be spent on consultancy costs and the remainder will be used to cover staffing resources, travelling expenses and co-ordinating activities.

2.6 The project will be delivered by the Intelligence Unit and Regeneration teams, drawing upon a mixture of existing and additional staffing resources. At this stage, it is anticipated that 2 FTE additional GLA staff (1 FTE per team) will be required to deliver the project at a cost of up to €160,500 (c. £134k). These new posts will be fully-funded by the European grant for the period of the project. Existing management and administration time to a value of €12,894 (c. £10k), evidenced by timesheets, will also be provided as the GLA’s contribution to the project.

3.1 The GLA as a public authority must comply with the Public Sector Equality Duty set out in section 149 (1) Equality Act 2010. This provides that, in the exercise of their functions, public authorities must have due regard to the need to:

• Eliminate discrimination, harassment, victimisation and any other conduct that is prohibited by or under the Equality Act 2010;
• Advance equality of opportunity between persons who share a relevant protected characteristic and persons who do not share it; and
• Foster good relations between persons who share a relevant protected characteristic and persons who do not share it.

a. The obligation in section 149(1) is placed upon the Mayor, as decision maker. Due regard must be had at the time a particular decision is being considered. The duty is non-delegable and must be exercised with an open mind.

b. This duty also applies in the delivery of European funded projects and means that delivery of this RICE funded project must consider the needs of all individuals and have due regard to the need to eliminate discrimination, advance equality of opportunity, and foster good relations between different people. The Project Manager will give due regard to the above when commissioning and designing the various strands of this programme and representing London on the EU wide steering group.

a) key risks and issues

Risk

Probability

Impact

Overall

Mitigation

Lack of dedicated resourcing – delays work plan, limits supervision and resulting transferability

2

3

2

Each partner has assigned dedicated staff resource to the project. This will be supplemented by EIB staff support and external consultancy support. A detailed work-plan will be developed.

Time/Budget constraints – limit scope of action, in particular activities which test wider relevance/transferability

2

3

2

The action has challenging objectives. Detailed consultancy terms of reference will be put in place and supervision proposals implemented. A detailed budget will be developed and this will be managed by The Hague. The GLA Project Manager will ensure they have sight of all relevant project documentation and access to an escalation process.

Lack of relevance of findings/recommendations, resulting in relevance to partners only

1

2

1

This will be addressed via wider consultation with other regions and interested stakeholders and dissemination events. A consultation plan will be developed.

On-going currency fluctuations and changes in the exchange rate lead to a shortfall in the GLA grant

2

2

2

The GLA claim will be paid in Euros by the lead partner. Exchange rate fluctuations between the claim date and the payment date may result in the GLA receiving less (or more) in £ sterling than it has claimed. GLA officers will seek advice from GLA Finance regarding establishing a Euro account to mitigate exchange rate risks, but in addition potential shortfalls against expenditure may be offset against savings on existing staff budgets resulting from the EU-funding income for this project.

Lack of skills and experience affects quality of outputs

2

3

2

The Consortium of Partners already has extensive experience in FI development and implementation. This will be supplemented by dedicated EIB staff and external consultants.

b) links to Mayoral strategies and priorities

The Mayor has promised to be the most pro-business Mayor that London has ever had. This has meant protecting small and technology businesses through public investment and protecting workspaces and ensuring businesses get a say in policy formulation through the formation of a Business Advisory Board. The Mayor is also keen that London gets the best deal possible in a post-Brexit scenario and is confident in the enduring strength of London’s deep-seated, competitive assets, which include its economic dynamism, a highly skilled workforce and an innovative and entrepreneurial culture.

All of these priorities will be enhanced by a better understanding of how to further unlock private sector investment to bolster London’s existing global leading sectors and also of potentially growing and emerging sectors. This project will help show that London is at the forefront of innovation and will also help to highlight the vast opportunities London offers to potential investors and business partners both home and abroad and will help ensure London stays open to the world.

5.1 The total award for this programme is €2.3m for which the GLA’s share is €244,976 (to be funded by the EU Commission) over 12-months. In addition, the GLA is required to provide match funding totalling €12,894 which will be in the form of staff time and contained within the existing Delivery & Intelligence Unit’s Staffing budgets. This will bring the total estimated gross cost of the project to €257,870. An estimated project budget is summarised below:

Proposed Expenditure €
Staffing resource 160,500
Travel & Subsistence 16,000
Consumables & Supplies 7,000
Dissemination of information / publications 7,500
Consultancy Support 50,000
Direct eligible costs (7%) 16,870
Total 257,870

5.2 It should be noted that the GLA will make claims for the reimbursement of costs from the EU in arrears based upon actual spend and will be paid in euros; consequently, there is the risk that the GLA will suffer from exchange rate losses and the income received will not cover the expenditure incurred. Whilst it is not possible to estimate how much the potential loss will be; the losses will be contained within the GLA’s Delivery & Intelligence Units staffing budgets via savings made upon staffing resources already budgeted for and utilised as part of this project.

5.3 Any changes to this project, including budgetary implications will be subject to further approval via the Authority’s decision-making process. All appropriate budget adjustments will be made.

6.1 The foregoing sections of this report indicate that:

6.1.1 the decisions requested of the Mayor concern the exercise of the GLA’s general powers, falling within the statutory powers of the GLA to do such things as may be considered necessary to further, and or be facilitative of or conducive or incidental to the furthering of, the promotion of wealth creation and economic development in Greater London and the making of investments where for any purpose relevant to its functions under any enactment, or for the purposes of the prudent management of its financial affairs; and

6.1.2 in formulating the proposals in respect of which a decision is sought officers have complied with the GLA’s related statutory duties to:

(a) pay due regard to the principle that there should be equality of opportunity for all people;
(b) consider how the proposals will promote the improvement of health of persons, health inequalities between persons and to contribute towards the achievement of sustainable development in the United Kingdom; and
(c) consult with appropriate bodies.

6.2 In taking the decisions requested, the Mayor must have due regard to the Public Sector Equality Duty; namely the need to eliminate discrimination, harassment, victimisation and any other conduct prohibited by the Equality Act 2010, and to advance equality of opportunity between persons who share a relevant protected characteristic (race, disability, gender, age, sexual orientation, religion or belief, pregnancy and maternity and gender reassignment) and persons who do not share it and foster good relations between persons who share a relevant protected characteristic and persons who do not share it (section 149 of the Equality Act 2010). To this end, the Mayor should have particular regard to section 3 (above) of this report.

6.3 Should the Mayor be minded to make the decisions sought Officers must ensure that they:

6.3.1 are content that the GLA can meet any conditions to which the RICE funding is subject seeking legal and finance advice as necessary;

6.3.2 do not act in reliance of such funding until The City of the Hague are obligated to the provision of the same (by way of a funding agreement or other legally binding document);

6.3.3 any services required for delivery of the project is procured by Transport for London Procurement who will determine the detail of the procurement strategy to be adopted in accordance with the GLA’s Contracts and Funding Code and appropriate contract documentation is put in place and executed by the successful bidder(s) and the GLA before the commencement of the services; and

6.3.4 comply fully with all GLA HR/Head of Paid Service protocols in respect of staffing proposals, in particular the need to gain all necessary approvals for the creation of any new posts.

Activity

Timeline

Project contracting, set up and recruitment

Dec - Feb 2017

Delivery Start Date for project proposals

Mar/Apr 2017

Publication of findings

March 2018

Delivery End Date for project proposals

March 2018

Project Closure: for project proposals

April 2018

Signed decision document

Need a document on this page in an accessible format?

If you use assistive technology (such as a screen reader) and need a version of a PDF or other document on this page in a more accessible format, please get in touch via our online form and tell us which format you need.

It will also help us if you tell us which assistive technology you use. We’ll consider your request and get back to you in 5 working days.